We're on 9.05.702
We've got some jobs that are scheduling parent assemblies to start before their child assemblies are finished. Is anyone aware of a field or setting
that would cause this? Parts are not setup as Phantom BOM's. Operations on both Asm levels are all finish-to-start, with no send ahead offsets.
Thanks in advance,