Part issue & receipt control

Farshad,



There are two for receipt "Receipt and Receipt from mfg". I have not worked
with these but most of the time you can run a message from the update
section of the method.



Steve



-----Original Message-----
From: farshad aboobacker [mailto:farshu4u@...]
Sent: January 15, 2008 1:18 AM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Part issue & receipt control



v\:* {behavior:url(#default#VML);}o\:* {behavior:url(#default#VML);}w\:*
{behavior:url(#default#VML);}..shape {behavior:url(#default#VML);}
Hi Steve,

We tried using BPM, but could only managean action (change status of job to
closed) after the event (issuing to job hasexceeded the required qty). Could
you please give some pointers on the BPM,like which business object to be
used in BPM and some basic details on thesame?

Regards,

Farshad

---------------------------------

From:vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
[mailto:vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com] On
Behalf Of vantage
Sent: Sunday, January 13, 20087:10 PM
To: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
Subject: RE: [Vantage] Part issue& receipt control

If you are on Version 8.03.400 you could use the BPMmodule to restrict
users to control this.

Steve

-----Original Message-----
From: farshad aboobacker [mailto:farshu4u@yahoo.
<mailto:farshu4u%40yahoo.com> com]
Sent: January 13, 2008 6:35 AM
To: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
Subject: [Vantage] Part issue & receipt control

Hi All,

Is there anyway we could control the issue of materials to a job, such that
the user does not issue more materials on the job without an approval?
Is there anyway we could stop the user from receiving more items into
Inventory from the Job using the Job Receipt to Inventory option, than the
Qty completed on the job?
Thank you and regards,

Farshad.

---------------------------------
Be a better friend, newshound, and know-it-all with Yahoo! Mobile. Try it
now.

[Non-text portions of this message have been removed]

[Non-text portions of this message have been removed]

---------------------------------
Be a better friend, newshound, and know-it-all with Yahoo! Mobile. Try it
now.

[Non-text portions of this message have been removed]





[Non-text portions of this message have been removed]
Hi All,


Is there anyway we could control the issue of materials to a job, such that the user does not issue more materials on the job without an approval?
Is there anyway we could stop the user from receiving more items into Inventory from the Job using the Job Receipt to Inventory option, than the Qty completed on the job?
Thank you and regards,

Farshad.


---------------------------------
Be a better friend, newshound, and know-it-all with Yahoo! Mobile. Try it now.

[Non-text portions of this message have been removed]
If you are on Version 8.03.400 you could use the BPM module to restrict
users to control this.



Steve



-----Original Message-----
From: farshad aboobacker [mailto:farshu4u@...]
Sent: January 13, 2008 6:35 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Part issue & receipt control



Hi All,


Is there anyway we could control the issue of materials to a job, such that
the user does not issue more materials on the job without an approval?
Is there anyway we could stop the user from receiving more items into
Inventory from the Job using the Job Receipt to Inventory option, than the
Qty completed on the job?
Thank you and regards,

Farshad.

---------------------------------
Be a better friend, newshound, and know-it-all with Yahoo! Mobile. Try it
now.

[Non-text portions of this message have been removed]





[Non-text portions of this message have been removed]
v\:* {behavior:url(#default#VML);}o\:* {behavior:url(#default#VML);}w\:* {behavior:url(#default#VML);}..shape {behavior:url(#default#VML);}
Hi Steve,



We tried using BPM, but could only managean action (change status of job to closed) after the event (issuing to job hasexceeded the required qty). Could you please give some pointers on the BPM,like which business object to be used in BPM and some basic details on thesame?



Regards,



Farshad




---------------------------------


From:vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of vantage
Sent: Sunday, January 13, 20087:10 PM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Part issue& receipt control




If you are on Version 8.03.400 you could use the BPMmodule to restrict
users to control this.

Steve

-----Original Message-----
From: farshad aboobacker [mailto:farshu4u@...]
Sent: January 13, 2008 6:35 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Part issue & receipt control

Hi All,

Is there anyway we could control the issue of materials to a job, such that
the user does not issue more materials on the job without an approval?
Is there anyway we could stop the user from receiving more items into
Inventory from the Job using the Job Receipt to Inventory option, than the
Qty completed on the job?
Thank you and regards,

Farshad.

---------------------------------
Be a better friend, newshound, and know-it-all with Yahoo! Mobile. Try it
now.

[Non-text portions of this message have been removed]

[Non-text portions of this message have been removed]






---------------------------------