Part Receive Time Changes in 702a

How does it affect PO's?

We use Receive time to both buffer our Jobs & PO's Due Dates.

Did you open a call with Epicor Support on this issue? 



--- In vantage@yahoogroups.com, <mitchelljohn@...> wrote:

Epicor has decided to change the way that Part and Part Class receive time affects MRP.  Instead of offsetting the due date of the job by the number of receive days (giving a buffer) it now keeps the job due date as the required date and offsets the due date of the last operation only!  Does anyone know of another way to offset job due dates with MRP??
Epicor has decided to change the way that Part and Part Class receive time affects MRP.  Instead of offsetting the due date of the job by the number of receive days (giving a buffer) it now keeps the job due date as the required date and offsets the due date of the last operation only!  Does anyone know of another way to offset job due dates with MRP??