Hello,
We’ve observed that “Receive Time” on PartPlant does not apply to the Company Default Calendar when being received to Inventory from a Job, as we would expect, however it applies to the last Operation/Resource on a Job. Is there a way to specify the Calendar used for Receive Time?
Edit: Looks like this pulls from the Site Configuration Calendar vs. the Company Configuration Calendar. Scheduling was assuming it used the Calendar from the last Operation/Resource since this was same as Site Calendar.