Reporting re-work on a job

I am using vantage 6.0 help file...question, under the following scenario how would re-work cost be captured (re-work cost being both labor and materials)


Using shop floor I report labor by starting an activity

Work on the product

Then report my labor by ending activity

If I need to scrap 2 of the 5 units I worked on I

I enter a scrap Qty of 2

Then enter my reason code

Then what?

How is my re-work labor cost calculated

How is my re-work material cost calculated


Thanks in advance





Paul Smith


________________________________


The information contained in this message is intended solely for the individual it is specifically and originally addressed. This message and its contents may contain confidential or privileged information. If you are not the intended recipient, you are hereby notified that any disclosure or distribution, or taking any action in reliance on the content of this information is strictly prohibited. If you received this message in error, please delete it from any computer and notify the sender. If you suspect that this message may have been altered, please notify the sender.


[Non-text portions of this message have been removed]