The resources set up for each plant.
You would need to set up resources in each plant to do the assy, assuming you are trying to capture costs and scheduling in those plants.
If you are only trying to "kit" the assy jobs and get the right parts to the right areas and are building for each sales order, Sales Kits may work well for you.
WHat version are you on?
Make to Order in each plant?
Brz in Mpls.
You would need to set up resources in each plant to do the assy, assuming you are trying to capture costs and scheduling in those plants.
If you are only trying to "kit" the assy jobs and get the right parts to the right areas and are building for each sales order, Sales Kits may work well for you.
WHat version are you on?
Make to Order in each plant?
Brz in Mpls.
--- In vantage@yahoogroups.com, Tony Hughes <thughes281@...> wrote:
>
>
> We're set up as one company, multiple plants.
> But while we have multiple "plants", only one plant makes components, though all plants build assemblies.
>
> What is the easiest way to set up these routers in the other plants?
>
> Do I need to recreate the resource group in each plant?
>
> Is there a simpler way to do assembly jobs without a router?
>
> Thank you for any advice
>