# Same material for multiple operations

**URL:** <https://www.epiusers.help/t/same-material-for-multiple-operations/53999>\
**Category:** Epicor ERP 10\
**Tags:** jobmtl\
**Created:** [March 27, 2019, 12:14pm UTC](https://www.epiusers.help/t/same-material-for-multiple-operations/53999 "2019-03-27T12:14:53Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Larry-CS](https://www.epiusers.help/letter_avatar_proxy/v4/letter/l/c67d28/32.png) [@Larry-CS](https://www.epiusers.help/u/Larry-CS)\
**Post date:** [March 27, 2019, 12:14pm UTC](https://www.epiusers.help/t/same-material-for-multiple-operations/53999/1 "2019-03-27T12:14:53Z")

</div>

We currently have all our raw materials for a job attached to the first operation. We would like to assign the material to the correct operation.  
The problem we’re having is that the same material can be used on multiple operations during the manufacturing process and the system only allows us to assign the material to one operation.  
What is the best way to handle this?

---

<div class="post-metadata">

**Author:** ![ehowe](https://www.epiusers.help/letter_avatar_proxy/v4/letter/e/5e9695/32.png) [@ehowe](https://www.epiusers.help/u/ehowe)\
**Post date:** [March 27, 2019, 1:18pm UTC](https://www.epiusers.help/t/same-material-for-multiple-operations/53999/2 "2019-03-27T13:18:14Z")

</div>

You can add the same material to the BOM twice and choose different required quantities and operations for each.