Stay on 404A with your hotfix.
Confirmed with Epicor (MP) this bug is present again on 404B.
UGH!!! When will they ever get it right...?
Thanks again,
Patty Buechler
Confirmed with Epicor (MP) this bug is present again on 404B.
UGH!!! When will they ever get it right...?
Thanks again,
Patty Buechler
--- In vantage@yahoogroups.com, "pvolkert365" <pvolkert@...> wrote:
>
> This problem has driven us nuts for 2 years. I finally convinced
> Support that it was happening to us. They sent us a fix program
for
> 404A, and built the fix into 404B.
>
> So for two years we had an ERP system that did not schedule
correctly
> for us. So many features were useless. But now it is fixed.
>
> If you tested 404B and it is not fixed, then you may have a
different
> problem. Our call number was 2735276MPS. We would do a backwards
> schedule and override constraints, and the scheduling would forward
> schedule from today's date. We are not going to 404B, but are on
> 404A with our fix program.
>
> -Peter Volkert
> Symetrics Industries
>
> --- In vantage@yahoogroups.com, "bpbuechler" <pbuechler@> wrote:
> >
> > Three things I am looking for:
> > 1. I am wondering if others out there have this business scenario
> > 2. Advice on how others handle this business scenario
> > 3. Confirm I have a bug on my hands
> >
> > Business Scenario is as follows:
> > a. Make to Order Job
> > b. Finished Good Part is not in inventory
> > c. Not all details of Assembly 0 is known at the time the job is
> > being engineered, but can get started on subassemblies.
> > d. Create Subassemblies, Engineer/Release Job, and Schedule.
> > e. Time and materials are now on Subassembly operations
> > f. Final specs are in and Job Engineering finishes engineering
> > remaining operations on Assembly 0.
> > g. Job is rescheduled with Backwards choosen with the Job Due
Date
> > of 5/30/08.
> >
> > I have tested on 8.03.403C, 8.03.404/A & B and found a major
issue.
> > All remaining load (operations started and operations to be
> started)
> > schedules forward from today's date. I have changed the Company
> > config setting to Allow Scheduling before Today and it makes no
> > difference. Oh...and I should mention the Operations are set to
> > Finish-to-Start Scheduling Factor.
> >
> > It should schedule backwards from the Job Due Date...not today's
> date
> > forward? This is a bug...right?
> >
> > Thanks in advance for your advice and comments.
> > Patty Buechler
> > UV Color
> >
>