While using the scheduling board, when I move one Op out, and forward schedule, using Assembly - Subsequent Operations, all operations move including preceding operations. It is like they are all locked together.
Any ideas?
While using the scheduling board, when I move one Op out, and forward schedule, using Assembly - Subsequent Operations, all operations move including preceding operations. It is like they are all locked together.
Any ideas?
Can you take a screen shot of your dashboard?
Can you also take screen shot of the Scheduling factor for the operations involved?
You are moving the Op into the future I guess?
Thanks, fixed it. Reduce WIP was checked in job priorities
Glad that you solved it. I guess you mean, Minimize WIP check box.
The scheduling engine is quite complex, most of the time the behavior changes are based on the setting. It took me a while to understanding…