I thought that I had seen in site configuration you could make it so time was deducted from an operation based on quantity completed instead on time clocked to a operation, but I cannot find that now. I recently moved from Kinetic to E10 when I changed companies was that a Kinetic feature?
I’m getting confused on what you mean by Time Deducted. If you set a job operation to “Quantity Only” reporting, the labor hours recorded are the JobOper.ProdStandard times the quantity entered. Is that what you’re looking for?
Yep that’s its thanks