Scheduling Order

Hi Everybody,

Need help about the scheduling order. We are on 405A and we do finite scheduling. We have some problems with the job other after the Calculate Global Scheduling Order. The order is not good, in other words the system puts jobs that they are due later than other one first. So, it's very difficult to set manually the good order after the scheduling processes. We have 5 priority codes from HIGH to LOW. I need a trick to get a better result to minimize the manual moves. Thanx.