Scheduling work center start date is the same day material arriv

We are in 8.03.409c and use recieve times at either the Partplant or Partclass level(partplant overrides the class entry) to back the due date of the material from its internal operation.

--- In vantage@yahoogroups.com, "Stuart Noble" <stuart@...> wrote:
>
> You might want to add a queue time to the start of the relevant
> Workcentre. However, this adds time to every operation across the whole
> schedule for that workcentre so tread carefully.
>
> Stuart Noble
> Thompson Meat Machinery
> stuart@...
> ' + 61 7 3803 6643
>
>
> ________________________________
>
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
> Of sccvantage123
> Sent: Friday, 1 April 2011 5:55 AM
> To: vantage@yahoogroups.com
> Subject: [Vantage] Scheduling work center start date is the same day
> material arrives?
>
>
>
>
> Hi
> We are 6.1 the problem we have is the start date on the operation that
> consumes the material is the same day the material is required in, the
> result is we have jobs starting late and late customer deliveries. Am I
> missing something?
>
> Thanks, Jeff
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
Hi
We are 6.1 the problem we have is the start date on the operation that consumes the material is the same day the material is required in, the result is we have jobs starting late and late customer deliveries. Am I missing something?

Thanks, Jeff
You might want to add a queue time to the start of the relevant
Workcentre. However, this adds time to every operation across the whole
schedule for that workcentre so tread carefully.

Stuart Noble
Thompson Meat Machinery
stuart@...
' + 61 7 3803 6643


________________________________

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of sccvantage123
Sent: Friday, 1 April 2011 5:55 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Scheduling work center start date is the same day
material arrives?




Hi
We are 6.1 the problem we have is the start date on the operation that
consumes the material is the same day the material is required in, the
result is we have jobs starting late and late customer deliveries. Am I
missing something?

Thanks, Jeff






[Non-text portions of this message have been removed]
Fyi..if the operation is the first operation in an assembly the system
will not schedule or honor queue time defined at the resource or
resource group level..



Rob Bucek

Production Control Manager

PH: (715) 284-5376 ext 311

Mobile: (715)896-0590

FAX: (715)284-4084

<http://www.dsmfg.com/>

(Click the logo to view our site) <http://www.dsmfg.com/>





From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Stuart Noble
Sent: Thursday, March 31, 2011 5:20 PM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Scheduling work center start date is the same day
material arrives?





You might want to add a queue time to the start of the relevant
Workcentre. However, this adds time to every operation across the whole
schedule for that workcentre so tread carefully.

Stuart Noble
Thompson Meat Machinery
stuart@... <mailto:stuart%40tmach.com.au>
' + 61 7 3803 6643


________________________________

From: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
[mailto:vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ] On
Behalf
Of sccvantage123
Sent: Friday, 1 April 2011 5:55 AM
To: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
Subject: [Vantage] Scheduling work center start date is the same day
material arrives?

Hi
We are 6.1 the problem we have is the start date on the operation that
consumes the material is the same day the material is required in, the
result is we have jobs starting late and late customer deliveries. Am I
missing something?

Thanks, Jeff

[Non-text portions of this message have been removed]





[Non-text portions of this message have been removed]
I am not familiar with 6.1 we started on 8.03 and currently are on 9.05. We have a field called Receive Time that can be set on the Part or Part Class. We are setting all parts to 1 so they will be due to arrive from the Supplier or received into inventory the day before the material is needed.

Nikki Vesely
Production Planner


--- In vantage@yahoogroups.com, "Rob Bucek" <rbucek@...> wrote:
>
> Fyi..if the operation is the first operation in an assembly the system
> will not schedule or honor queue time defined at the resource or
> resource group level..
>
>
>
> Rob Bucek
>
> Production Control Manager
>
> PH: (715) 284-5376 ext 311
>
> Mobile: (715)896-0590
>
> FAX: (715)284-4084
>
> <http://www.dsmfg.com/>
>
> (Click the logo to view our site) <http://www.dsmfg.com/>
>
>
>
>
>
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
> Of Stuart Noble
> Sent: Thursday, March 31, 2011 5:20 PM
> To: vantage@yahoogroups.com
> Subject: RE: [Vantage] Scheduling work center start date is the same day
> material arrives?
>
>
>
>
>
> You might want to add a queue time to the start of the relevant
> Workcentre. However, this adds time to every operation across the whole
> schedule for that workcentre so tread carefully.
>
> Stuart Noble
> Thompson Meat Machinery
> stuart@... <mailto:stuart%40tmach.com.au>
> ' + 61 7 3803 6643
>
>
> ________________________________
>
> From: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
> [mailto:vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ] On
> Behalf
> Of sccvantage123
> Sent: Friday, 1 April 2011 5:55 AM
> To: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
> Subject: [Vantage] Scheduling work center start date is the same day
> material arrives?
>
> Hi
> We are 6.1 the problem we have is the start date on the operation that
> consumes the material is the same day the material is required in, the
> result is we have jobs starting late and late customer deliveries. Am I
> missing something?
>
> Thanks, Jeff
>
> [Non-text portions of this message have been removed]
>
>
>
>
>