So, went to set Min’s and Max’s and they reverted back to the original. It seems there is a Monday recalc setup that seems to revert it back. I couldn’t find much in the guides, but i may of missed it. Any info on this would work. also going back through the guides to make sure I didn’t miss.

While in Epicor 10.1 a Min Max Safety Mass update program was added, that I know of it cannot be scheduled. Could it be that someone unintentionally used the program to update your Min & Max?
What version are you on?
Min\Max and other planning parameter changes are some of the fields that I’ve ended up setting up Change Log Data Directives due to some confusion about who and when these critical settings change.
Or are you saying that when you set them manually that they reverted back… a step by step and timeline would be helpful.
Thanks!

-Rick
www.getaligned.solutions

1 Like

@Rick_Bird Thanks for the response. So, here is the timeline for you.

On Friday at 2:30 my guy put in new Min and Max’s for certain parts in Part Maintenance. On Monday morning, it went back to what it was before it was changed on Friday; so reverted back.

We are using version 10.1.400.19.