Robert,
I am trying to understand how to set up subcontract in Vantage 8 and
found this message from you through a search in the Vantage group. I
tried following the steps you outlined and have a few questions.
The subcontract operation we are trying to add comes in between parts
moving from one plant to another. I don't know if you have
experience with this or not, but would it be better to set the
subcontract in the plant that does the first operation or the plant
that does the final operation? Also, you mention setting the
subcontract OPs in the MOM as back-flush...where is this done? I see
where you can mark a part as backflush, but can you mark an operation
as such? Once all of this is done and you run MRP...will you get a
suggestion to open a job or just the PO?
Sorry for the seemingly stupid questions, but I am a self taught user
and sometimes the obvious isn't so obvious.
Thanks
Cindy
--- In vantage@yahoogroups.com, Robert Brown <robertb_versa@...>
wrote:
robotically create what you intend to be a SubContract OP as a normal
OP.
Operations (that effectively represent all your normal capacity
consumption combinations of resources and/or resources groups and/or
capabilities). This makes it very easy for an ME to create OPs for
methods by simply entering the standard OP and then adding specific
set up time & run rate info for the part. If you have tools/fixtures
set up as resources the ME may also manually add a specific tool or
fixture needed on the part's MoM OP to the resource list.
want to have an approved vendor pre-associated with it. Even if it is
a subcontract service that you may have a choice of multiple vendors
for, you still want to have the Std OP refer to your typical primary
vendor for the subcontract service.
Upon Receipt, the OP will be qty reported complete in the same qty as
was received (and, if Inspection Required is indicated on the PO, by
the qty that passed inspection). This qty then flows back into Job
WIP - ready for the next OP to be processed.
I am trying to understand how to set up subcontract in Vantage 8 and
found this message from you through a search in the Vantage group. I
tried following the steps you outlined and have a few questions.
The subcontract operation we are trying to add comes in between parts
moving from one plant to another. I don't know if you have
experience with this or not, but would it be better to set the
subcontract in the plant that does the first operation or the plant
that does the final operation? Also, you mention setting the
subcontract OPs in the MOM as back-flush...where is this done? I see
where you can mark a part as backflush, but can you mark an operation
as such? Once all of this is done and you run MRP...will you get a
suggestion to open a job or just the PO?
Sorry for the seemingly stupid questions, but I am a self taught user
and sometimes the obvious isn't so obvious.
Thanks
Cindy
--- In vantage@yahoogroups.com, Robert Brown <robertb_versa@...>
wrote:
>Subcontract. It is all too easy when creating or modifying a MoM to
> First: Look at the job details and verify the OP is checked as
robotically create what you intend to be a SubContract OP as a normal
OP.
>recommended path): It is advantageous to pre-create Standard
> Second: Set up all your subcontract OPs in your MoMs as back-flush.
>
> Third (based on an assumption you are following vantage's
Operations (that effectively represent all your normal capacity
consumption combinations of resources and/or resources groups and/or
capabilities). This makes it very easy for an ME to create OPs for
methods by simply entering the standard OP and then adding specific
set up time & run rate info for the part. If you have tools/fixtures
set up as resources the ME may also manually add a specific tool or
fixture needed on the part's MoM OP to the resource list.
>the 'subcontract' checkbox in the Operation maintenance app), you
> For subcontract Standard OPs (which is indicated by checking
want to have an approved vendor pre-associated with it. Even if it is
a subcontract service that you may have a choice of multiple vendors
for, you still want to have the Std OP refer to your typical primary
vendor for the subcontract service.
>into the MoM with no additional effort.
> Now, when you create a MoM with this Std OP, the vendor info flows
>method SubContract OP that has an approved vendor associated with it.
> Creating a Job using this MoM then creates a back-flush labor entry
>requirement, your Jobs WIP up to this OP is shipped to the vendor.
> When Purchasing cuts a PO to fulfill the subcontract service
Upon Receipt, the OP will be qty reported complete in the same qty as
was received (and, if Inspection Required is indicated on the PO, by
the qty that passed inspection). This qty then flows back into Job
WIP - ready for the next OP to be processed.
>I
> Easy? :)
>
> Rob Brown
>
> --- On Tue, 7/8/08, nmtaylor1969 <n.taylor@...> wrote:
>
> From: nmtaylor1969 <n.taylor@...>
> Subject: [Vantage] Sub-Contract Operation In 8.03.305K
> To: vantage@yahoogroups.com
> Date: Tuesday, July 8, 2008, 5:54 AM
>
>
>
>
>
>
> Does anybody know how I close a sub-contract operation ? ( in other
> words I am expecting to see the little green tick in the op list ).
> am sure there is something I am doing wrong, but I can't see what.over, as
>
> I believe this operation is also causing my scheduling to fall
> the job doesn't seem to schedule properly, but I get no error. Onthat
> note, does anybody know why I see a red cube and not a blue cube inthe
> job scheduling board. This makes me suspicious!
>
> Thanks,
>
> Nick Taylor
>