Hi Mega Hive Mind
We have an interesting problem when it comes to Subcon PO the due date of when it returns to us is wrong and i mean really wrong sometimes it even adds the wrong year, Not to sure where to even start looking.
When i print the report the dates match up with the system but im not sure its the right date to be using. Any help would be great thank you again.
So the Po its been noticed the dates say date of order 14/01/2025 and due date is the 4/11/2025 witch is massively wrong would woudl expect it back in 33 days.