Our re-testing Thursday was successful. The problems initially encountered appeared to have been a result of issues with imported data (most likely method OpDtl data and/or part-vendor related data).
Lessons learned:
1. The subcontract OP does NOT have to be the last OP in the Job. (Whew!)
2. It does not matter whether the subcontract PO is set as Inspection Required or not.
3. It does not matter if the subcontract OP is set up as a Labor activity Back-flush (versus quantity) reporting - other than one caveat:
If you make it quantity reporting and the activity is going to reported via 8.03.404 MES, MES has a bug that screws up the process (leaving the OP appear open even though fully qty reported).
404 MES does NOT auto-set the 2 related db tables' Job OP completion status fields to complete (value=true) even when the full OP qty is reported as done.
This appears to be the case for any reportable OP (not just subcontract).
The standard Labor Entry app DOES correctly set these fields so it is not an issue unless your activity reporting users are limited to lower cost MES licenses.
Perhaps the just released 404A corrects the problem (although I saw nothing in the release notes to indicate that is true).
The only area unconfirmed was verification that cost flowed correctly into the Jobs WIP and, subsequently, into inventory after Job Receipt. (Planned to be tested on a more general level in the near future.)
Thanks for the help Jim. Much appreciated.
Rob Brown
Jim Frice <Jim.Frice@...> wrote: I just tested a couple subcontract receipts here and it flagged the
operation as complete. We don't have inspection turned on for any of
these. Are the quantity received equal to or greater than the required
quantity for the demand? Make sure the issued complete is checked on the
receipt or being unchecked by accident.
Jim
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Robert Brown
Sent: Wednesday, March 12, 2008 6:22 AM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] subcontract
Transactions are there. The subcontract op just isn't being flagged as
complete (even after successful inspection processing of the subcontract
receipt).
We're going to be going thru the process again tomorrow in detail. I'm
hoping to find some easy to fix data set up problem (since it worked OK
before v404).
Thanks
Rob Brown
Mike McGee <mmcgee@... <mailto:mmcgee%40flexial.com> > wrote:
??? We use this all the time. If the po is received and the inspection
processing is done, it should work. Do you see the transactions in job
tracker?
_____
From: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
[mailto:vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ] On
Behalf Of
Robert Brown
Sent: Friday, March 07, 2008 3:30 PM
To: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
Subject: RE: [Vantage] subcontract
Still no joy. No OP status compete even after inspection processing
complete/
Possibly some final trigger I'm unaware of?
Thx
Rob Borwn
Mike McGee <mmcgee@flexial. <mailto:mmcgee%40flexial.com> com> wrote:
The
inspection processing must be completed and dispositioned in order for
the operation to close.
_____
From: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
[mailto:vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com] On
Behalf Of
Robert Brown
Sent: Friday, March 07, 2008 3:12 PM
To: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
Subject: RE: [Vantage] subcontract
Again, in our 404 testing yesterday, we did that to the letter - but the
subcontract operation was NOT automatically closed upon receipt of the
subcontract PO.
All of our subcontract processing is also set for receipt inspection
required (which may or may not be a contributing factor to the observed
behavior problem).
Even after processing subcontract PO receipt inspection, the subcontract
OP
still was not automatically set as status complete.
Any ideas?
Rob Brown
Mike McGee <mmcgee@flexial. <mailto:mmcgee%40flexial.com> com> wrote:
When
the subcontract operation is added to the job, be sure it is entered as
a subcontract operation.
Enter your vendor information on the job.
You have a choice on Pos between Inventory - other- Job material - or
subcontract operation - select subcontract operation.
When the PO is received it will automatically close the operation on the
job
and transfer the cost from the PO to the job.
Mike
_____
From: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
[mailto:vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com] On
Behalf Of
Bill Finn
Sent: Friday, March 07, 2008 1:48 PM
To: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
Subject: [Vantage] subcontract
Is anyone using the subcontract functionality? We sometimes see that
even
though the job is complete, when we try to do a job receipt to inventory
there is no value in the Quantity Completed box. I am thinking that it
may
be due to our shipper not using the Subcontractor Shipment when these
subcontrat items leave our facility to go to the sub. any input would be
greatly appreciated.
thanks
bill
---------------------------------
Never miss a thing. Make Yahoo your homepage.
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
---------------------------------
Looking for last minute shopping deals? Find them fast with Yahoo!
Search.
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
---------------------------------
Never miss a thing. Make Yahoo your homepage.
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
---------------------------------
Looking for last minute shopping deals? Find them fast with Yahoo!
Search.
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
---------------------------------
Be a better friend, newshound, and know-it-all with Yahoo! Mobile. Try it now.
[Non-text portions of this message have been removed]
Lessons learned:
1. The subcontract OP does NOT have to be the last OP in the Job. (Whew!)
2. It does not matter whether the subcontract PO is set as Inspection Required or not.
3. It does not matter if the subcontract OP is set up as a Labor activity Back-flush (versus quantity) reporting - other than one caveat:
If you make it quantity reporting and the activity is going to reported via 8.03.404 MES, MES has a bug that screws up the process (leaving the OP appear open even though fully qty reported).
404 MES does NOT auto-set the 2 related db tables' Job OP completion status fields to complete (value=true) even when the full OP qty is reported as done.
This appears to be the case for any reportable OP (not just subcontract).
The standard Labor Entry app DOES correctly set these fields so it is not an issue unless your activity reporting users are limited to lower cost MES licenses.
Perhaps the just released 404A corrects the problem (although I saw nothing in the release notes to indicate that is true).
The only area unconfirmed was verification that cost flowed correctly into the Jobs WIP and, subsequently, into inventory after Job Receipt. (Planned to be tested on a more general level in the near future.)
Thanks for the help Jim. Much appreciated.
Rob Brown
Jim Frice <Jim.Frice@...> wrote: I just tested a couple subcontract receipts here and it flagged the
operation as complete. We don't have inspection turned on for any of
these. Are the quantity received equal to or greater than the required
quantity for the demand? Make sure the issued complete is checked on the
receipt or being unchecked by accident.
Jim
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Robert Brown
Sent: Wednesday, March 12, 2008 6:22 AM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] subcontract
Transactions are there. The subcontract op just isn't being flagged as
complete (even after successful inspection processing of the subcontract
receipt).
We're going to be going thru the process again tomorrow in detail. I'm
hoping to find some easy to fix data set up problem (since it worked OK
before v404).
Thanks
Rob Brown
Mike McGee <mmcgee@... <mailto:mmcgee%40flexial.com> > wrote:
??? We use this all the time. If the po is received and the inspection
processing is done, it should work. Do you see the transactions in job
tracker?
_____
From: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
[mailto:vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ] On
Behalf Of
Robert Brown
Sent: Friday, March 07, 2008 3:30 PM
To: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
Subject: RE: [Vantage] subcontract
Still no joy. No OP status compete even after inspection processing
complete/
Possibly some final trigger I'm unaware of?
Thx
Rob Borwn
Mike McGee <mmcgee@flexial. <mailto:mmcgee%40flexial.com> com> wrote:
The
inspection processing must be completed and dispositioned in order for
the operation to close.
_____
From: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
[mailto:vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com] On
Behalf Of
Robert Brown
Sent: Friday, March 07, 2008 3:12 PM
To: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
Subject: RE: [Vantage] subcontract
Again, in our 404 testing yesterday, we did that to the letter - but the
subcontract operation was NOT automatically closed upon receipt of the
subcontract PO.
All of our subcontract processing is also set for receipt inspection
required (which may or may not be a contributing factor to the observed
behavior problem).
Even after processing subcontract PO receipt inspection, the subcontract
OP
still was not automatically set as status complete.
Any ideas?
Rob Brown
Mike McGee <mmcgee@flexial. <mailto:mmcgee%40flexial.com> com> wrote:
When
the subcontract operation is added to the job, be sure it is entered as
a subcontract operation.
Enter your vendor information on the job.
You have a choice on Pos between Inventory - other- Job material - or
subcontract operation - select subcontract operation.
When the PO is received it will automatically close the operation on the
job
and transfer the cost from the PO to the job.
Mike
_____
From: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
[mailto:vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com] On
Behalf Of
Bill Finn
Sent: Friday, March 07, 2008 1:48 PM
To: vantage@yahoogroups <mailto:vantage%40yahoogroups.com> .com
Subject: [Vantage] subcontract
Is anyone using the subcontract functionality? We sometimes see that
even
though the job is complete, when we try to do a job receipt to inventory
there is no value in the Quantity Completed box. I am thinking that it
may
be due to our shipper not using the Subcontractor Shipment when these
subcontrat items leave our facility to go to the sub. any input would be
greatly appreciated.
thanks
bill
---------------------------------
Never miss a thing. Make Yahoo your homepage.
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
---------------------------------
Looking for last minute shopping deals? Find them fast with Yahoo!
Search.
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
---------------------------------
Never miss a thing. Make Yahoo your homepage.
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
---------------------------------
Looking for last minute shopping deals? Find them fast with Yahoo!
Search.
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
---------------------------------
Be a better friend, newshound, and know-it-all with Yahoo! Mobile. Try it now.
[Non-text portions of this message have been removed]