Most of my EPICOR knowledge is on the financial side rather than the manufacturing side. Our manufacturing division has a question that I am hoping you all would be able to point me in the right direction on.
What is the best way to transfer a worker’s time and materials from one job to another?
Materials would be in Return Material from old job and Issue Material to new job.
For changing the time, you can use Time and Expense Entry. Go to the workers sheet and date. Go to the tabs Time > Daily Time > Detail and locate the desired entry. Recall the transaction, change the job number and select the new Assembly Seq, and Operation Seq. Hit submit and all that time should then be on the second job and not on the first one.