Tracking sub-contracted assemblies

I posted the same message about 2 weeks ago. Vantage does not handle
this well. If you would like, call me and I will explain how we are
handling this.

I am only in the office until 3:30. (eastern time)

Dina Hieber
Vamco International, Inc.
(412) 963-7100

singlefire2001 wrote:

> I have a few parts that are either manufactured or purchased and are
> used in assemblies on a "1-per" basis. The parts (2) are sent to a
> welder and assembled into a finished part. The part number is
> different than the components (obviously). Does Vantage hide a quick
> trick to be able to send these components to the welder and recieve
> them back as the finished part number without losing traceability of
> the components or the finished part? The problem lies in getting the
> materials both finished and sub-level to adjust their inventories
> without doing it manually.
>
>
>
>
> Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must
> have already linked your email address to a yahoo id to enable access.
> )
> (1) To access the Files Section of our Yahoo!Group for Report Builder
> and Crystal Reports and other 'goodies', please goto:
> http://groups.yahoo.com/group/vantage/files/.
> (2) To search through old msg's goto:
> http://groups.yahoo.com/group/vantage/messages
> (3) To view links to Vendors that provide Vantage services goto:
> http://groups.yahoo.com/group/vantage/links
>
> Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.

--
Dina M. Hieber
Vamco International, Inc.
555 Epsilon Drive
Pittsburgh, PA 15238
(412) 963-7100 - phone
(412) 963-9511 - fax

www.vamcointernational.com



[Non-text portions of this message have been removed]
I have a few parts that are either manufactured or purchased and are
used in assemblies on a "1-per" basis. The parts (2) are sent to a
welder and assembled into a finished part. The part number is
different than the components (obviously). Does Vantage hide a quick
trick to be able to send these components to the welder and recieve
them back as the finished part number without losing traceability of
the components or the finished part? The problem lies in getting the
materials both finished and sub-level to adjust their inventories
without doing it manually.