Transferring costs from a job and project to a new job and project

We currently have a sales order, job, and project under customer “A” and need to switch it over to customer “B”. Since there are already labor transactions and purchased material on this job is there a way to transfer the information from this sales order, job, and project if we set up a new sales order, job, and project under the customer “B”

Thank you in advance!

One option would be to change the demand link on the current job to Make to Job. Then you could receive whatever the part number is to the new job and all of the costs will transfer.

2 Likes

Thanks @jkane, wasn’t my post, but I just did this for the first time and it worked like a charm. CFO is very pleased!