Vantage 8.0 MRP Aborts

We are running production Vantage on 8.08D and a test server on 8.09.
We have a very large database - thousands of jobs with long BOM's. In
both versions of Vantage small errors in engineering jobs will cause
MRP to hang and run endlessly. Basically it never finishes. Is there a
way to verify a job is engineered correctly before releasing it to
MRP? We have sent a request to the Vantage call desk to have the logic
changed to time out and bypass problem jobs - simply flag them as not
completing. Other MRP systems I have worked with do this so the entire
run is not lost. Comments welcome.

Joe La Bore
Microdynamics Corp