Hello,
I hope somebody can help me? Our current version is 8.03.408B and I am having trouble with the costing workbench and pull as assembly.
When I rollup the costs in the Workbench any Child item marked within the Engineering Workbench as Pull as Assembly (on the Method of Manufacture -> Material Tab) doesn't include labour and burden anywhere in the top level parent part; i.e. it is just missing it hasn't been included in Material for example.
As soon as Pull as Assembly is unticked the rollup works correctly, the total cost on the parent part is higher by the previously missing labour and burden, however Pull as Assembly is an important part of our manufacturing systems and can't just be unticked.
Has anybody got any ideas as to what may be causing this issue and any suggestions as to how I can resolve it.
Kind Regards
Matthew
I hope somebody can help me? Our current version is 8.03.408B and I am having trouble with the costing workbench and pull as assembly.
When I rollup the costs in the Workbench any Child item marked within the Engineering Workbench as Pull as Assembly (on the Method of Manufacture -> Material Tab) doesn't include labour and burden anywhere in the top level parent part; i.e. it is just missing it hasn't been included in Material for example.
As soon as Pull as Assembly is unticked the rollup works correctly, the total cost on the parent part is higher by the previously missing labour and burden, however Pull as Assembly is an important part of our manufacturing systems and can't just be unticked.
Has anybody got any ideas as to what may be causing this issue and any suggestions as to how I can resolve it.
Kind Regards
Matthew