Kanban is Rob's best friend. LOL



Kanban sucks a$$.



From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
Jose Gomez
Sent: Thursday, April 11, 2013 4:20 PM
To: Vantage
Subject: [Vantage] Oh Kan Ban < 1





Hi All
Here is a fun one,
We just discovered that ANY Kan Ban job with a production Qty of less than
1 but greater than 0 so anything that is a "Partial" unit gets issued the
wrong amount of materials For Example

We have a Mom for Part XXX which requires 2 PPP Parts Per if we create a
Kan Ban job for .5 XXX this is what ends up happening

It correctly calculates a Required Qty of 1 PPP since originally it
required 2 PPP and we are cutting that in 1/2

But then at Issue time it once again divides the required qty in half
Issuing only .5 PPP

Has anyone seen this?

*Jose C Gomez*
*Software Engineer*
*
*
*
*T: 904.469.1524 mobile
E: jose@... <mailto:jose%40josecgomez.com>
http://www.josecgomez.com
<http://www.linkedin.com/in/josecgomez> <http://www.facebook.com/josegomez>
<http://www.google.com/profiles/jose.gomez> <http://www.twitter.com/joc85>
<http://www.josecgomez.com/professional-resume/>
<http://www.josecgomez.com/feed/>
<http://www.usdoingstuff.com>

*Quis custodiet ipsos custodes?*

[Non-text portions of this message have been removed]





[Non-text portions of this message have been removed]