Who is using advanced planning module, in a high mix / low volume production?

I would like to know if anybody is using the advance planning module in a high mix / low volume production, to share experience, setting etc…

thanks’

Arnaud

How advanced are you looking to get? We’re a fully custom shop cranking out 5-10 orders a day but everything is different on the jobs.

We are a factory of 150 worker ,go live passed in april, now we are experimenting the planning module in pain. We have about 600-700 jobs in progress in the workshop, 10K parts 56K lines of bom, 23K lines of BOO transferred.