WIP report in Epicor 9 not reporting completed parts correctly

Has anyone ever ran across an issue where the Epicor 9 WIP report doesn’t report the completed quantity on a job correctly on some jobs?  We have some jobs that didn’t complete totally but the WIP report says they did but the total to Inventory field DOES match the ACTUAL number of parts that DID complete.  Just the total completed does not.   Any idea???

 