--- In vantage@y..., Roy Bosworth <royb@k...> wrote:
> Does anybody have a problem with the "materials" value being
incorrect on
> their WIP report? We have gone into the database and found that the
> information there, is correct but yet the WIP report is wrong.
Only the
> materials cost's are incorrect for totals. Any information on this
would be
> helpful considering that Epicor wants a copy of our database and
the problem
> is in the report. Go figure............
>
> Roy Bosworth
> Senior Manager IT/MIS
> 818-503-8100
>
>
> -----Original Message-----
> From: Lydia Coffman [mailto:lcoffman@c...]
> Sent: Thursday, February 01, 2001 9:19 AM
> To: vantage@y...
> Subject: RE: [Vantage] Inventory/WIP Reconciliation (Vantage 4:902)
>
>
> Our accountant says it took a lot long to run that report today
also ( on
> 4:904)-our assumption is the greater number of records because of
MRP
> functionality, even though we don't have MRP.
>
> This is our first regular month's closing in 4.0.
>
> Lydia
>
>
> -----Original Message-----
> From: Plaman Dick [mailto:dick.plaman@T...]
> Sent: Thursday, February 01, 2001 8:58 AM
> To: 'vantage@y...'
> Subject: [Vantage] Inventory/WIP Reconciliation (Vantage 4:902)
>
> When the Inventory/WIP Reconcilication Report is run, (Ver4:902),
it takes a
> very long time to get output. Also, frequent crashes have been
occuring.
> In Ver 3, this procedure took only 5 minutes. We have experienced
this
> problem since going to Ver 4.
> Is this a common problem, or am I alone here?
> Thanks,
>
>
> To unsubscribe from this group, send an email to:
> vantage-unsubscribe@egroups.com
To unsubscribe from this group, send an email to:
vantage-unsubscribe@egroups.com
--- In vantage@y..., Roy Bosworth <royb@k...> wrote:
> Does anybody have a problem with the "materials" value being
incorrect on
> their WIP report? We have gone into the database and found that the
> information there, is correct but yet the WIP report is wrong.
Only the
> materials cost's are incorrect for totals. Any information on this
would be
> helpful considering that Epicor wants a copy of our database and
the problem
> is in the report. Go figure............
>
> Roy Bosworth
> Senior Manager IT/MIS
> 818-503-8100
>
>
> -----Original Message-----
> From: Lydia Coffman [mailto:lcoffman@c...]
> Sent: Thursday, February 01, 2001 9:19 AM
> To: vantage@y...
> Subject: RE: [Vantage] Inventory/WIP Reconciliation (Vantage 4:902)
>
>
> Our accountant says it took a lot long to run that report today
also ( on
> 4:904)-our assumption is the greater number of records because of
MRP
> functionality, even though we don't have MRP.
>
> This is our first regular month's closing in 4.0.
>
> Lydia
>
>
> -----Original Message-----
> From: Plaman Dick [mailto:dick.plaman@T...]
> Sent: Thursday, February 01, 2001 8:58 AM
> To: 'vantage@y...'
> Subject: [Vantage] Inventory/WIP Reconciliation (Vantage 4:902)
>
> When the Inventory/WIP Reconcilication Report is run, (Ver4:902),
it takes a
> very long time to get output. Also, frequent crashes have been
occuring.
> In Ver 3, this procedure took only 5 minutes. We have experienced
this
> problem since going to Ver 4.
> Is this a common problem, or am I alone here?
> Thanks,
>
>
> To unsubscribe from this group, send an email to:
> vantage-unsubscribe@egroups.com
--- In vantage@y..., Roy Bosworth <royb@k...> wrote:
> Does anybody have a problem with the "materials" value being
incorrect on
> their WIP report? We have gone into the database and found that the
> information there, is correct but yet the WIP report is wrong.
Only the
> materials cost's are incorrect for totals. Any information on this
would be
> helpful considering that Epicor wants a copy of our database and
the problem
> is in the report. Go figure............
>
> Roy Bosworth
> Senior Manager IT/MIS
> 818-503-8100
>
>
> -----Original Message-----
> From: Lydia Coffman [mailto:lcoffman@c...]
> Sent: Thursday, February 01, 2001 9:19 AM
> To: vantage@y...
> Subject: RE: [Vantage] Inventory/WIP Reconciliation (Vantage 4:902)
>
>
> Our accountant says it took a lot long to run that report today
also ( on
> 4:904)-our assumption is the greater number of records because of
MRP
> functionality, even though we don't have MRP.
>
> This is our first regular month's closing in 4.0.
>
> Lydia
>
>
> -----Original Message-----
> From: Plaman Dick [mailto:dick.plaman@T...]
> Sent: Thursday, February 01, 2001 8:58 AM
> To: 'vantage@y...'
> Subject: [Vantage] Inventory/WIP Reconciliation (Vantage 4:902)
>
> When the Inventory/WIP Reconcilication Report is run, (Ver4:902),
it takes a
> very long time to get output. Also, frequent crashes have been
occuring.
> In Ver 3, this procedure took only 5 minutes. We have experienced
this
> problem since going to Ver 4.
> Is this a common problem, or am I alone here?
> Thanks,
>
>