Sent: Thursday, April 21, 2005 11:59 AM
Subject: Re: [Vantage] Scheduling Subcontracting operations


>
> Hi All,
>
> I couple weeks ago I posted a message regarding the way the system
schedules
> subcontracting work - basically the fact that is does not taken into
account
> when a subcontract operation has already started. I finally was able to
> speak Epicor support about this issue and it turns out that there is
already
> an enhancement request and an SCR created for this (see below). So, just
> wanted to let you all know and if anyone else has this issue, please add
> your name to it so it will get prioritized.
>
> Thanks,
> Sarah
> -----------------------------------------------------------
>
> Page 668BRK
>
> Vantage 6.10.502
> es/esp10.w
> 1. Production management -> job management -> GO -> job entry
> Add a job for any part, and any quantity.
> Make sure the required by date is today.
> 2. Add a subcontract operation to the job.
> Any vendor.
> Make sure the days out is 10 days.
> 3. Release and schedule the job.
> Note that the start date of the subcontract operation is 10 days before
> today.
> 4. Materials management -> Shipping / receiving -> GO ->
> Subcontractor shipment entry.
> Ship the subcontract operation.
> 5. Production management -> scheduling -> GO -> Global finite
> scheduling
> Schedule start date is tomorrow. Schedule
> 6. Production management -> job management -> GO -> job tracker
> Select the job and view the subcontract operation details
> Note that the start date of the operation is tomorrow.
> It is not possible to move the operation because the parts are already
> shipped and will be returned in 10 days.
>
> Development response
> ==================
>
> SCR 7943
>
> Since at least Vantage 5.00, Global Finite Scheduler code (es/esp10-bu.p
and
> es/esp10-cm.p) has considered an operation to be started if it has any
labor
> activity. But subcontract operations never have this. For subcontract
> operations, if the Global Reschedule Started Operations is checked in Job
> Management Configuration, the operation should not be changed if it has
any
> related part transactions (PartTran records).
>
>
> Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must
have already linked your email address to a yahoo id to enable access. )
> (1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
> (2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
> (3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
> Yahoo! Groups Links
>
>
>
>
>
>
>
>