Hi All,
Another scheduling problem we have encountered.
We attempt to schedule operations through a bottle neck workcentre using
Load Levelling.
All the operations move, but the entire job stays where it was except
for the moved operations. This makes no logical sense at all. Is there
anything I am missing in the setup?
For example I have a job with 6 operations spanning a month period. It
passes through the same workcentre twice. I drag the operations around
on the workcentre load schedule, and bring the two operations a week
forward. All the other operations remain where they were, including the
operation between the two moved operations. The part cannot be made
logically because middle operation isn't scheduled for a week, but needs
to be done before the second moved operation can commence.
If anyone can offer any thoughts on ways to work around this problem, I
would be very appreciative. Seems moving operations cannot work without
looking at a job specific scenario. Would seem much quicker to schedule
allowing other changes to also occur around what you are moving. Then
you could just smooth the overloaded workcentres created by the plan to
manage schedule by the problem workcentre.
Thanks a lot.
Stuart Noble
Thompson Meat Machinery
stuart@...
' + 61 7 3803 6643
[Non-text portions of this message have been removed]
Another scheduling problem we have encountered.
We attempt to schedule operations through a bottle neck workcentre using
Load Levelling.
All the operations move, but the entire job stays where it was except
for the moved operations. This makes no logical sense at all. Is there
anything I am missing in the setup?
For example I have a job with 6 operations spanning a month period. It
passes through the same workcentre twice. I drag the operations around
on the workcentre load schedule, and bring the two operations a week
forward. All the other operations remain where they were, including the
operation between the two moved operations. The part cannot be made
logically because middle operation isn't scheduled for a week, but needs
to be done before the second moved operation can commence.
If anyone can offer any thoughts on ways to work around this problem, I
would be very appreciative. Seems moving operations cannot work without
looking at a job specific scenario. Would seem much quicker to schedule
allowing other changes to also occur around what you are moving. Then
you could just smooth the overloaded workcentres created by the plan to
manage schedule by the problem workcentre.
Thanks a lot.
Stuart Noble
Thompson Meat Machinery
stuart@...
' + 61 7 3803 6643
[Non-text portions of this message have been removed]