> This is a fun little bug.
>
>
>
> Assuming you don't have AMM (as we don't) and you're getting this
> message, here's the fix:
>
>
>
> 1. Go into the resource group entry for the related resource
that
> you're trying to issue against and go to the detail tab.
>
> 2. There are 3 warehouse fields, In/Out/Backflush. Click in
each
> field, even if they're empty or gray.
>
> 3. Make some other change (add a character to the description
for
> instance)
>
> 4. Click Save
>
> 5. Repeat for each resource under the resource group
(clicking the
> fields and changing the description), hitting save on each resource
>
>
>
> Basically you're forcing the system to update the warehouses by
making
> some change and clicking into the others.
>
>
>
> Ken
>
>
>
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On
Behalf
> Of c.chest
> Sent: Monday, October 06, 2008 6:03 AM
> To: vantage@yahoogroups.com
> Subject: [Vantage] AMM warehouse/bin issue
>
>
>
> When trying to move a job material to the material queue in "Get
> Request", I keep getting a message that the To warehouse and the To
bin
> cannot be blank. Can anyone tell me what this means and how I fix
it?
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
When trying to move a job material to the material queue in "Get
Request", I keep getting a message that the To warehouse and the To bin
cannot be blank. Can anyone tell me what this means and how I fix it?
This is a fun little bug.



Assuming you don't have AMM (as we don't) and you're getting this
message, here's the fix:



1. Go into the resource group entry for the related resource that
you're trying to issue against and go to the detail tab.

2. There are 3 warehouse fields, In/Out/Backflush. Click in each
field, even if they're empty or gray.

3. Make some other change (add a character to the description for
instance)

4. Click Save

5. Repeat for each resource under the resource group (clicking the
fields and changing the description), hitting save on each resource



Basically you're forcing the system to update the warehouses by making
some change and clicking into the others.



Ken



From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of c.chest
Sent: Monday, October 06, 2008 6:03 AM
To: vantage@yahoogroups.com
Subject: [Vantage] AMM warehouse/bin issue



When trying to move a job material to the material queue in "Get
Request", I keep getting a message that the To warehouse and the To bin
cannot be blank. Can anyone tell me what this means and how I fix it?





[Non-text portions of this message have been removed]
Check out what you have setup in the Resource Group (Resource)
Maintenance. Each Resource Group and Resource has it's own Input
Whse/Bin and Output Whse/Bin.

Note: A bug still remains that it does not pick up the Input Resource
Whse/Bin from where the NEXT OPR is scheduled to run. It still pulls
from the RG (dumb logic that still remains from 8.0).

A couple places where the moves can be tracked are as follows:
Job Tracker - Part Location
Part Tracker - Part Location (if not moving to next opr, you can view
WIP in the Part Location of the Finished Good Part).

Hope this helps.
Patty Buechler



--- In vantage@yahoogroups.com, "c.chest" <c.chest@...> wrote:
>
> When trying to move a job material to the material queue in "Get
> Request", I keep getting a message that the To warehouse and the To
bin
> cannot be blank. Can anyone tell me what this means and how I fix it?
>
Thank you...worked like a charm!

--- In vantage@yahoogroups.com, "bpbuechler" <pbuechler@...> wrote:
>
> Check out what you have setup in the Resource Group (Resource)
> Maintenance. Each Resource Group and Resource has it's own Input
> Whse/Bin and Output Whse/Bin.
>
> Note: A bug still remains that it does not pick up the Input
Resource
> Whse/Bin from where the NEXT OPR is scheduled to run. It still
pulls
> from the RG (dumb logic that still remains from 8.0).
>
> A couple places where the moves can be tracked are as follows:
> Job Tracker - Part Location
> Part Tracker - Part Location (if not moving to next opr, you can
view
> WIP in the Part Location of the Finished Good Part).
>
> Hope this helps.
> Patty Buechler
>
>
>
> --- In vantage@yahoogroups.com, "c.chest" <c.chest@> wrote:
> >
> > When trying to move a job material to the material queue in "Get
> > Request", I keep getting a message that the To warehouse and the
To
> bin
> > cannot be blank. Can anyone tell me what this means and how I
fix it?
> >
>