Do you have materials attached to the backflushed operation?
I am not sure whether vantage backflushes at the point of labour
entry. It does for some reason when you enter the job tracker.
I would like to see your routing.
Do you have materials attached to the backflushed operation?
I am not sure whether vantage backflushes at the point of labour
entry. It does for some reason when you enter the job tracker.
I would like to see your routing.
--- In vantage@yahoogroups.com, "Babette Welch" <bwelch@a...> wrote:
> We are running Vantage 6.1
>
> Our operations and 'method of labor entry' are
> <<ole0.bmp>>
>
>
> When we enter labor with qty and/or time
> it is inconsistent if the preceding operations back flush.
>
> We have run Job > Back flush Operations
> with no change in the results.
>
> It seems to happen with the data-entry operation marked as both T
or Q.
>
> Why does it back flush labor sometimes and not other times?
>
>
> BW
> _________________________________________________
> Babette Welch
> IT Director
> Argonics, Inc
> 1110 Wright Street
> Marquette MI 49855
> 906.226.9747 ext 235
> 906.228.0951
>
>
>