By-products in 6.1

Scott,

Thanks for the information. I've got the process working now. We
were trying to adjust the cost of the job using the the Issue /
Return screen. (Much like Jerry's group, I think). After posting
my message, I began digging around and found the Salvage Part field
and kept experimenting until I got it worked out. I ended up doing
what you recommended. (I receive the messages in digest form and
had hammered it out by the time I got your suggestion.)

The biggest challenge was the fact that my machined part actually is
purchased in two stock sizes, with different costs (material per
foot + fixed machining cost). The part is a component in a
configurator product, which can only determine how much to use, not
which size piece to start with (this could be done with 2 part
numbers, but that also complicates it). I was able to manage this
by using both Dimensional Inventory and Lot Costing. It still only
works if complete pieces are issued to the job regardless of actual
length required. I put instructions in the Material Comments as
well as in the Lot and Dimensional descriptions.

All the costs are captured, my inventory is correct and my
controller can stop having a cow about the "but it's still good"
scrap inventory that one of my production managers insists on
keeping.


Thanks again for everyone's help,
Michael Randolph
Purchasing Manager
American Magnetics, Inc.


--- In vantage@yahoogroups.com, "Lepley, Scott A." <sal@m...> wrote:
> Jerry,
>
> Unfortunately, I cannot explain why your job costs are not reduced.
> Whenever we have used this function, the costs of the salvaged
material were
> automatically entered by the system based on the costs stored in
the part
> master record. While the user can modify these calculated costs,
I believe
> we have never done so. However, there have been situations where
we needed
> to create a new part record in the part master so that we could
salvage that
> part from a job. In these cases, we also established unit costs
for the new
> part via the cost adjustment function. As far as I know, the job
costs
> have always been reduced appropriately. We have not used this
functionality
> extensively, but it seemed to me that it fit as a solution to
Michael's
> problem.
>
> Regards,
> Scott
>
> -----Original Message-----
> From: Aaron Hoyt [mailto:aaron.hoyt@v...]
> Sent: Friday, December 17, 2004 10:27 AM
> To: vantage@yahoogroups.com
> Subject: RE: [Vantage] By-products in 6.1
>
> Jerry,
> We are just setting this up 6.1.514.
> We set up the expected salvage in the job material with the
salvage part
> number and value.
> We receive the salvage material from the job, enter the quantity
we are
> receiving. If you click ok we get a message about salvage
material Labor
> credit can't exceed the material labor cost....If you look at the
boxes in
> the lower right for values, you can enter the material cost and
0.00 out the
> labor and burden costs for the salvage material.
> Then receive the part with only a material cost and a quantity and
it will
> allow the receipt.
> The production detail report will reflect the receipt and cost are
adjusted
> properly.
> Does this help solve your issue Jerry?
> Good luck,
> Aaron Hoyt
> Vantage Plastics
>
> -----Original Message-----
> From: Jerry Boyle [mailto:jboyle@s...]
> Sent: Friday, December 17, 2004 9:51 AM
> To: vantage@yahoogroups.com
> Subject: RE: [Vantage] By-products in 6.1
>
> Scott, we have used the salvage function but it will not reduce
the material
> cost correctly. If you are salvaging material #2 and have not
issued any to
> the job you must make the "cost" of the salvaged material $0. It
will
> correctly return it to inventory but the job gets $0 "credit".
You can not
> have a less than $0 cost, but you can have a less than 0 quantity.
> We do not issue any of the by-product material to the job but want
the
> material cost to be lowered by the value of the by-product. If
you are able
> to get the salvage function to correctly do this, we would like to
know your
> method.
>
> Thanks,
> Jerry Boyle, Controller
> Sipco Molding Technologies
> Meadville, PA. 16335
> p 814.724.2243 x53
> f 814.724.2244
> vantage 6.10
>
> -----Original Message-----
> From: Lepley, Scott A. [mailto:sal@m...]
> Sent: Friday, December 17, 2004 9:08 AM
> To: 'vantage@yahoogroups.com'
> Subject: RE: [Vantage] By-products in 6.1
>
> This seems like an ideal situation for using the salvage materials
function.
> You can use this function if you can reuse modified materials from
a job.
> Salvage materials are entered as inventory receipt transactions,
and reduce
> the material cost against specific jobs. Have you looked at
this? If so,
> was there some limitation that posed a problem for you?
>
> Regards,
> Scott Lepley
> Systems Administrator
> Mauell Corporation
> Phone: 717-432-8686, ext. 14
> Fax: 717-432-8688
> Email: sal@m...
> Vantage version: 6.10.514
>
>
> [Non-text portions of this message have been removed]
There was a thread several days ago about managaing by-products in
Vantage. If I remember correctly, this isn't a strong point for
Vantage. I would love some suggestions for the following process,
but I realize that the well may be empty on this.

We purchase a 20' tube (a stock length) with 1 machined end. We
then cut the tube to length to meet specific customer projects,
leaving a usable piece of un-machined tube. This tube can be sent
back to the machine shop to be turned a shorter version of the
original 20' purchased tube. Ideally, we could issue 20' of Tube-M
(machined) to the job and return 8' of Tube-UM. The two need to be
tracked differently because the machining is a significant portion
of the machined part. I think the previoius thread said this wasn't
possible in 6.1

Has anyone created a work-around?

Thanks

Michael Randolph'
Purchasing Manager
American Magnetics, Inc.
This seems like an ideal situation for using the salvage materials function.
You can use this function if you can reuse modified materials from a job.
Salvage materials are entered as inventory receipt transactions, and reduce
the material cost against specific jobs. Have you looked at this? If so,
was there some limitation that posed a problem for you?
Regards,
Scott Lepley
Systems Administrator
Mauell Corporation
Phone: 717-432-8686, ext. 14
Fax: 717-432-8688
Email: sal@...
Vantage version: 6.10.514

-----Original Message-----
From: ami_miker [mailto:michael.randolph@...]
Sent: Friday, December 17, 2004 8:46 AM
To: vantage@yahoogroups.com
Subject: [Vantage] By-products in 6.1


There was a thread several days ago about managaing by-products in
Vantage. If I remember correctly, this isn't a strong point for
Vantage. I would love some suggestions for the following process,
but I realize that the well may be empty on this.

We purchase a 20' tube (a stock length) with 1 machined end. We
then cut the tube to length to meet specific customer projects,
leaving a usable piece of un-machined tube. This tube can be sent
back to the machine shop to be turned a shorter version of the
original 20' purchased tube. Ideally, we could issue 20' of Tube-M
(machined) to the job and return 8' of Tube-UM. The two need to be
tracked differently because the machining is a significant portion
of the machined part. I think the previoius thread said this wasn't
possible in 6.1

Has anyone created a work-around?

Thanks

Michael Randolph'
Purchasing Manager
American Magnetics, Inc.



[Non-text portions of this message have been removed]
Scott, we have used the salvage function but it will not reduce the material
cost correctly. If you are salvaging material #2 and have not issued any to
the job you must make the "cost" of the salvaged material $0. It will
correctly return it to inventory but the job gets $0 "credit". You can not
have a less than $0 cost, but you can have a less than 0 quantity.
We do not issue any of the by-product material to the job but want the
material cost to be lowered by the value of the by-product. If you are able
to get the salvage function to correctly do this, we would like to know your
method.

Thanks,
Jerry Boyle, Controller
Sipco Molding Technologies
Meadville, PA. 16335
p 814.724.2243 x53
f 814.724.2244
vantage 6.10

-----Original Message-----
From: Lepley, Scott A. [mailto:sal@...]
Sent: Friday, December 17, 2004 9:08 AM
To: 'vantage@yahoogroups.com'
Subject: RE: [Vantage] By-products in 6.1


This seems like an ideal situation for using the salvage materials function.
You can use this function if you can reuse modified materials from a job.
Salvage materials are entered as inventory receipt transactions, and reduce
the material cost against specific jobs. Have you looked at this? If so,
was there some limitation that posed a problem for you?
Regards,
Scott Lepley
Systems Administrator
Mauell Corporation
Phone: 717-432-8686, ext. 14
Fax: 717-432-8688
Email: sal@...
Vantage version: 6.10.514
Jerry,
We are just setting this up 6.1.514.
We set up the expected salvage in the job material with the salvage part
number and value.
We receive the salvage material from the job, enter the quantity we are
receiving. If you click ok we get a message about salvage material Labor
credit can't exceed the material labor cost....If you look at the boxes in
the lower right for values, you can enter the material cost and 0.00 out the
labor and burden costs for the salvage material.
Then receive the part with only a material cost and a quantity and it will
allow the receipt.
The production detail report will reflect the receipt and cost are adjusted
properly.
Does this help solve your issue Jerry?
Good luck,
Aaron Hoyt
Vantage Plastics

-----Original Message-----
From: Jerry Boyle [mailto:jboyle@...]
Sent: Friday, December 17, 2004 9:51 AM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] By-products in 6.1



Scott, we have used the salvage function but it will not reduce the material
cost correctly. If you are salvaging material #2 and have not issued any to
the job you must make the "cost" of the salvaged material $0. It will
correctly return it to inventory but the job gets $0 "credit". You can not
have a less than $0 cost, but you can have a less than 0 quantity.
We do not issue any of the by-product material to the job but want the
material cost to be lowered by the value of the by-product. If you are able
to get the salvage function to correctly do this, we would like to know your
method.

Thanks,
Jerry Boyle, Controller
Sipco Molding Technologies
Meadville, PA. 16335
p 814.724.2243 x53
f 814.724.2244
vantage 6.10

-----Original Message-----
From: Lepley, Scott A. [mailto:sal@...]
Sent: Friday, December 17, 2004 9:08 AM
To: 'vantage@yahoogroups.com'
Subject: RE: [Vantage] By-products in 6.1


This seems like an ideal situation for using the salvage materials function.
You can use this function if you can reuse modified materials from a job.
Salvage materials are entered as inventory receipt transactions, and reduce
the material cost against specific jobs. Have you looked at this? If so,
was there some limitation that posed a problem for you?
Regards,
Scott Lepley
Systems Administrator
Mauell Corporation
Phone: 717-432-8686, ext. 14
Fax: 717-432-8688
Email: sal@...
Vantage version: 6.10.514




Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
Yahoo! Groups Links
Jerry
We use salvage a lot. We will issue a 12" X 24" X 72" piece of
graphite to a job by pounds under part # GB012.00X24X072-HLM (1000
lbs., $2/lb, $2000 mtl cost). Then salvage a GB006X24X072*HLM back to
inventory at $2/lb, 500 lbs., $1000 mtl cost. Also a GB006X12X024*HLM
for $1/lb 167 lbs, $167 mtl cost. Mtl cost left in the job is $833.
Were running 5.2
HTH
Russ Dover


To: <vantage@yahoogroups.com>
From: "Jerry Boyle" <jboyle@...>
Subject: RE: [Vantage] By-products in 6.1

> Scott, we have used the salvage function but it will not reduce the
> material
> cost correctly. If you are salvaging material #2 and have not issued
> any to
> the job you must make the "cost" of the salvaged material $0. It will
> correctly return it to inventory but the job gets $0 "credit". You
> can not
> have a less than $0 cost, but you can have a less than 0 quantity.
> We do not issue any of the by-product material to the job but want the
> material cost to be lowered by the value of the by-product. If you
> are able
> to get the salvage function to correctly do this, we would like to
> know your
> method.
>
> Thanks,
> Jerry Boyle, Controller
> Sipco Molding Technologies
> Meadville, PA. 16335
> p 814.724.2243 x53
> f 814.724.2244
> vantage 6.10
>
> -----Original Message-----
> From: Lepley, Scott A. [mailto:sal@...]
> Sent: Friday, December 17, 2004 9:08 AM
> To: 'vantage@yahoogroups.com'
> Subject: RE: [Vantage] By-products in 6.1
>
>
> This seems like an ideal situation for using the salvage materials
> function.
> You can use this function if you can reuse modified materials from a
> job.
> Salvage materials are entered as inventory receipt transactions, and
> reduce
> the material cost against specific jobs. Have you looked at this?
> If so,
> was there some limitation that posed a problem for you?
> Regards,
> Scott Lepley
> Systems Administrator
> Mauell Corporation
> Phone: 717-432-8686, ext. 14
> Fax: 717-432-8688
> Email: sal@...
> Vantage version: 6.10.514
>
>
>
> Useful links for the Yahoo!Groups Vantage Board are: ( Note: You
> must have already linked your email address to a yahoo id to enable
> access. )
> (1) To access the Files Section of our Yahoo!Group for Report Builder
> and Crystal Reports and other 'goodies', please goto:
> http://groups.yahoo.com/group/vantage/files/.
> (2) To search through old msg's goto:
> http://groups.yahoo.com/group/vantage/messages
> (3) To view links to Vendors that provide Vantage services goto:
> http://groups.yahoo.com/group/vantage/links
>
>
Jerry,

Unfortunately, I cannot explain why your job costs are not reduced.
Whenever we have used this function, the costs of the salvaged material were
automatically entered by the system based on the costs stored in the part
master record. While the user can modify these calculated costs, I believe
we have never done so. However, there have been situations where we needed
to create a new part record in the part master so that we could salvage that
part from a job. In these cases, we also established unit costs for the new
part via the cost adjustment function. As far as I know, the job costs
have always been reduced appropriately. We have not used this functionality
extensively, but it seemed to me that it fit as a solution to Michael's
problem.

Regards,
Scott

-----Original Message-----
From: Aaron Hoyt [mailto:aaron.hoyt@...]
Sent: Friday, December 17, 2004 10:27 AM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] By-products in 6.1

Jerry,
We are just setting this up 6.1.514.
We set up the expected salvage in the job material with the salvage part
number and value.
We receive the salvage material from the job, enter the quantity we are
receiving. If you click ok we get a message about salvage material Labor
credit can't exceed the material labor cost....If you look at the boxes in
the lower right for values, you can enter the material cost and 0.00 out the
labor and burden costs for the salvage material.
Then receive the part with only a material cost and a quantity and it will
allow the receipt.
The production detail report will reflect the receipt and cost are adjusted
properly.
Does this help solve your issue Jerry?
Good luck,
Aaron Hoyt
Vantage Plastics

-----Original Message-----
From: Jerry Boyle [mailto:jboyle@...]
Sent: Friday, December 17, 2004 9:51 AM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] By-products in 6.1

Scott, we have used the salvage function but it will not reduce the material
cost correctly. If you are salvaging material #2 and have not issued any to
the job you must make the "cost" of the salvaged material $0. It will
correctly return it to inventory but the job gets $0 "credit". You can not
have a less than $0 cost, but you can have a less than 0 quantity.
We do not issue any of the by-product material to the job but want the
material cost to be lowered by the value of the by-product. If you are able
to get the salvage function to correctly do this, we would like to know your
method.

Thanks,
Jerry Boyle, Controller
Sipco Molding Technologies
Meadville, PA. 16335
p 814.724.2243 x53
f 814.724.2244
vantage 6.10

-----Original Message-----
From: Lepley, Scott A. [mailto:sal@...]
Sent: Friday, December 17, 2004 9:08 AM
To: 'vantage@yahoogroups.com'
Subject: RE: [Vantage] By-products in 6.1

This seems like an ideal situation for using the salvage materials function.
You can use this function if you can reuse modified materials from a job.
Salvage materials are entered as inventory receipt transactions, and reduce
the material cost against specific jobs. Have you looked at this? If so,
was there some limitation that posed a problem for you?

Regards,
Scott Lepley
Systems Administrator
Mauell Corporation
Phone: 717-432-8686, ext. 14
Fax: 717-432-8688
Email: sal@...
Vantage version: 6.10.514


[Non-text portions of this message have been removed]
Thanks to everyone who responded on this. I had never actually used this
function myself - I was relaying info from our Production Manager and his
scheduler / material manager. I was able to make it work after reading
everyone's comments. Apparently they were listing the by-product as a
material requirement (0 qty) on the job and trying to salvage from it ! (go
figure)

Jerry Boyle, Controller
Sipco Molding Technologies
Meadville, PA. 16335
p 814.724.2243 x53
f 814.724.2244
vantage 6.10