Hi all,
I’d like to start using the Resource Schedule Load Graph, and I found this earlier post:
Which refers to this KB article:
https://epiccare.epicor.com/epiccare?id=epiccare_kb_article&sys_id=400b72c61b451490907e62007e4bcba0
There’s some overlap in the processes mentioned with this other post:
Can anyone add any clarity on what the difference is between these processes? Why do I need to run 6 different processes just to use this report? For instance, why do I need to reload / rebuild / refresh shop load 3 times?!
Summary of the KB article:
Run these from the conversion workbench.
- 710 - Create/Rebuild ShopLoad information
- 650 - cvjc0071 This program rebuilds Shopload records.
- 640 - cvJC0069 To create/fix the ShopCap.Capacity totals
- 590 - cves0003 Refresh ShopLoad Table
NOTE: Run one at a time in order of 710, 650, 640, 590
- The Generate Shop Capacity Process needs to be run next
- The last thing which needs to be run is Schedule Process Set = zScheduleLoadGraph