Best suggestion yet, Rick.
Deb Wilmoth
Controller
Reeder & Kline Machine Company, Inc.
Vantage 5.0
-----Original Message-----
From: Rick Gors [mailto:rgors@...]
Sent: Wednesday, September 10, 2003 1:33 PM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Costing / Bean Counter Question
Seems to me if you buy these parts for a specific job (or jobs), then they
will automatically be costed to the job(s) as WIP material. Then when you
ship they will roll into COS.
[Non-text portions of this message have been removed]
Deb Wilmoth
Controller
Reeder & Kline Machine Company, Inc.
Vantage 5.0
-----Original Message-----
From: Rick Gors [mailto:rgors@...]
Sent: Wednesday, September 10, 2003 1:33 PM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Costing / Bean Counter Question
Seems to me if you buy these parts for a specific job (or jobs), then they
will automatically be costed to the job(s) as WIP material. Then when you
ship they will roll into COS.
[Non-text portions of this message have been removed]