Dmr on a coparts job

With a Coparts job producing parts A & B , Is there a way to issue a DMR on just part A ?

Hi Adam,

The best way to DMR a copart is to take both parts to stock, then you can DMR just Part A from stock, leaving Part B in stock. If they are already in Inspection Processing from an Operation or Job Material, pass them back, take them both to stock, then Nonconform only Part A that is defective.

I did hear at Insights 2023 (Safe Harbor :safe_harbor:) Epicor is working on a way to nonconform just one of the parts from a job.

2 Likes

Nice! thanks for the guidance!

Happy to help!