Does anyone know of a way to designate different time frames within the same work week as the standard shift?

Why not make a shift for the staggered schedule? Or you could have a
series of shifts that could be selected from.

Just a thought...

Rick Gors
MR/MMIS
Osco

PHIL LUKOMSKI wrote:
>
> We are implementing staggered shifts. It is possible that an employee would start and finish at different times during the work week. Unfortunately we only see that the default 'master' shift for each employee can only be defined by one timeframe. Does anyone know of a way to designate different time frames within the same work week as the standard shift?
>
> Thanks
> Phil
>
> We no longer allow attachments to files. To access/share Report Files, please go to the following link: http://www.egroups.com/files/vantage/
> (Note: If this link does not work for you the first time you try it, go to www.egroups.com, login and be sure to save your password, choose My Groups, choose Vantage, then choose Files. If you save the password, the link above will work the next time you try it.)