Hi,
I have the following scenario using Scheduling Factor Finish-To-Start and a production calendar of Monday - Friday 08:00 - 16:00.
Op 1 - 2 hours - Start 16/06/2025 08:00 - Due 16/06/2025 10:00
Op 2 - 2 hours - Start 16/06/2025 10:00 - Due 16/06/2025 12:00
Op 3 - 8 hours - Start 16/06/2025 12:00 - Due 17/06/2025 12:00
Op 4 - 1 hours - Start 17/06/2025 12:00 - Due 17/06/2025 13:00
Op 5 - 1 hours - Start 17/06/2025 13:00 - Due 17/06/2025 14:00
However, Op3 and Op4 can start after a batch of 2 have finished Op 2.
If I chage the Scheduling Factor to Start-To-Start and Send Ahead Type to Pieces and Send Ahead Offset to 2 then Op 4 will finish before Op 2 and Op 3 which doesn’t make sense.
Does anyone else tackle this type of production line problem?