I have parts with three ops.
Op10 completed 24 hour before op20 and op30.
I do not want op20 and op30 to ever “split up”. That is if op20 is scheduled to start 3/24 there must be enough time for op30 to start and complete on 3/24. If not both op20 and op30 must schedule to start the next day 3/25 for example. Currently op20 can schedule to start 3/24 and op 30 can schedule to start 3/25. This does not fit our process and results in confusion.
Both ops utilize the same finite resources, as such I can not simply allow op30 to be infinite.
Has anyone encountered something similar? Likewise combining ops 20 and 30 is not an option.
Thanks,
