Global Scheduling vs MRP who goes first

,

We are looking to run global scheduling over the weekend. What order would you run global scheduling with regards to MRP? Before or after?

I run Global Scheduling after MRP. Below is my nightly task set that our consultant help us set up.
I’m open to any suggestions if something looks out of place.
image

2 Likes

Thanks Matt! That’s really helpful.