Global Scheduling vs MRP who goes first

,

We are looking to run global scheduling over the weekend. What order would you run global scheduling with regards to MRP? Before or after?

I run Global Scheduling after MRP. Below is my nightly task set that our consultant help us set up.
I’m open to any suggestions if something looks out of place.
image

Thanks Matt! That’s really helpful.