How can I make a MOM so the following happen

when you add subassembly 1 make it "related to" op 30 of assembly 0 and then it will schedule as you have shown below. If we are building extra for inventory we add inventory demand link. If we are running extra of a specific subassembly because we think we may need extras for the job, we add an overrun qty on that. If we are running extras for a few operations that we think we may scrap, we add a scrap qty onto those operations.


To help drive material.

 

10/1

10/2

10/3

10/4

10/5

10/6

10/7

10/8

10/9

10/10

10/11

10/12

10/13

10/14

Assm 0

OP10

 

OP20

 

 

OP30

 

 

 

 

OP40

 

SubAssm1

OP10

 

OP20

 

 

 

 

 

OP30

 

SubAsm 1 Op 30 is complete, it needs to go to Op30 of Asm 0

 

 

http://imgur.com/a/IORrf

 

 

I want to my sub assembly to start a week earlier than my top assembly.

 

They also asked how can we drive to build more than what the Order states.

                So if I enter an order for 100, I want to build 2 to inventory.  I was thinking a BPM on JobHead Update to look for that PN and then take the Order Demand + add 2 Inventory Demand.

 

Miguel A. Santillan

 



Disclaimer

The information contained in this communication from the sender is confidential. It is intended solely for use by the recipient and others authorized to receive it. If you are not the recipient, you are hereby notified that any disclosure, copying, distribution or taking action in relation of the contents of this information is strictly prohibited and may be unlawful.