When I Close a project what will happen…
I need to know what financial traction will happen and what happened to to the revenue recognition i had done manually…any functional opinion is appreciated…becoz im connered
When I Close a project what will happen…
I need to know what financial traction will happen and what happened to to the revenue recognition i had done manually…any functional opinion is appreciated…becoz im connered
What do you mean close a project? I’m not following your post.
Hello Arun,
The first thing that happens is that the project gets closed and cannot be re-opened with standard Epicor functionality. There are posts here where some have created a UBAQ to change the flag but it’s not standard Epicor.
Depending on your billing method, there are some transactions based around retention and reversing recognition. (See the Contract | Detail tab in the lower right-hand corner).
Your best bet is to just test it out in a Pilot database to make sure it does what you think with your settings.