Indented BOM cost BAQ

I am a total newb when it comes to writing a BAQ like this. Basically, I would like some guidance, possibly an example, of writing an indented bom cost baq. I think I have a decent start but need to incorporate a set of fields I cannot find. The fields I need are in the view cost on the method tracker and they are the unit cost fields. Can anyone point me in that direction?

@Compton here is my go to link on indented boms, but if you search there are other threads also. I can tie most of the view costs for my boms to PartCost. I usually check for values FLA or first, last average from PartCost. There are some that for me also require PartUOM when the base uom is not the usage uom on the bom to get the usage cost from the purchased cost. We have subs that we build and stock and I was not able to figure out how to tie those back to labor and burden costs in method tracker.

1 Like

Thank you. That was a great help! I now have my BAQ almost complete

2 Likes