Job Manager Showing Incorrect Demand

I have a Laminate Part A.

When I look at it Job Manager, in the ‘Demand’ pane, it shows 4 jobs that shouldn’t be there.
Each job is for a completely different laminate part, and indicates the demand is because Laminate Part A is a material on each of these 4 jobs.

Opening the 4 offending jobs in job entry/tracker, these jobs have no material (which is correct) and these jobs were complete/closed back in Feb.

There are also 2 more jobs in the demand pane, but these jobs are accurate and behaving as expected.

When I look at this part in Time Phase the 4 offending jobs do not show up, everything looks correct.