Job start date issue

We’re testing some jobs in our test environment and orders entered with a required date of +4 weeks from now with jobs of 4 weeks in duration are all being scheduled with to start 1st NOV!

There are no long lead time parts. Any pointers?

Thanks

Matt

Hard to speculate without more details.
Times depend on many factors. e.g. your shop load, method structure, stock/nonstock mtls, finite/infinite etc…
I usually start by elevating the logging level(s) to see if those might provide any clues too. e.g. “MRP and Scheduling”

Hi Bruce,

Looks like the defaults on the MRP screen got saved incorrectly. MRP start date had changed to +6 months when it just should have been cutoff.

Thanks

Matt