Full schedule log for Op 20 is below, Op 30 worked/looked fine in the log, correct start time of 11.18. And i didn’t double paste into here, it ran scheduling on Op 20 twice?
11:57:04 Scheduling resource OP20 RESOURCE for : ScheduleDate 2025-05-16 FirstProdHour 0 LastProdHour 11.18 (getBackwardDateTime) — GetBackwardDateTime
11:57:04 UsingCalendarForMove of 24 Setting Move Due Time. MoveDueDate: 2025-05-16 MoveDueHour: 11.18 — GetBackwardDateTime
11:57:04 Setting Move start time according to production calendar. MoveStartDate: 2025-05-15 MoveStartHour: 11.82 — GetBackwardDateTime
Schedule Log
— MakeOperCal
11:57:04 Setup Master
11:57:04 Backward Scheduling - Job 293772 Asm 0 Opr 20 OpDtl 10 AllocationBlock - 1 For: Enddate - 2025-05-16 EndHour - 11.18 Endtime 1 Setup/Prod/Both B. tmpendtime 627155.18. — OpDtlBkProduction
11:57:04 ***Scheduling resource OP20 RESOURCE for 0 hours — processResourceID
11:57:04 Backward Scheduling OP20 RESOURCE for 0 hours on 2025-05-16 with a EndTime of 11.18 IP-ProcTime 11.18. — processResourceID
11:57:04 Infinitely scheduling OP20 RESOURCE FiniteHorizonDate 2025-04-23 ScheduleDate 2025-05-16 — GetBackwardDateTime
11:57:04 Found 2025-05-16 as a valid working date IP-ProcTime = 40248 — GetBackwardDateTime
11:57:04 Found 2025-05-16 as a valid working date — GetBackwardDateTime
11:57:04 Scheduling resource OP20 RESOURCE starting at time: 2025-05-16 11.18 (getBackwardDateTime) — GetBackwardDateTime
11:57:04 Scheduling resource OP20 RESOURCE for : ScheduleDate 2025-05-16 FirstProdHour 0 LastProdHour 11.18 (getBackwardDateTime) — GetBackwardDateTime
11:57:04 UsingCalendarForMove of 24 Setting Move Due Time. MoveDueDate: 2025-05-16 MoveDueHour: 11.18 — GetBackwardDateTime
11:57:04 Looking for Main production Calendar: OP20 RESOURCE — getWorkingCalendarHours
11:57:04 Looking for Main production Calendar: OP20 RESOURCE — getWorkingCalendarHours
11:57:04 Setting Move start time according to production calendar. MoveStartDate: 2025-05-15 MoveStartHour: 11.82 — GetBackwardDateTime
11:57:04 Looking for previous scheduled time on resource OP20 RESOURCE before 2025-05-15 and a start hour of 11.18 — GetBackwardDateTime
11:57:04 Looking to Schedule 0 Hours Ending on 2025-05-15 and an end hour of 11.82 (getPrevTotalAvailProdTime) — GetPrevTotalAvailProdTime
11:57:04 Zero hours to schedule setting Start date to Start time to 0 (getPrevTotalAvailProdTime) — GetPrevTotalAvailProdTime
11:57:04 Scheduled start time for resource OP20 RESOURCE for 2025-05-15 and a start hour of 11.82 — GetBackwardDateTime
11:57:04 Scheduling Resource OP20 RESOURCE for job 293772 Operation 20 Priority 100 StartDate 2025-05-15 EndDate 2025-05-15. — processResourceID
11:57:04 Setting Queue start time according to production calendar. QueueStartDate: 2025-05-15 QueueStartHour: 11.82 — _addQueueAndMoveTimesToAvailableResource
11:57:04 ***Done Scheduling Resource OP20 RESOURCE for job 293772 Operation 20 Priority 100 StartDate 2025-05-15 EndDate 2025-05-15 Move Date 2025-05-16. — processResourceID
11:57:04 *First available time for Resource OP20 RESOURCE is 2025-05-15 at 42552 (11.82) ending on 2025-05-15 at 11.82 for 0 hours. Move Date 2025-05-16 Move Hour 11.18. — processResourceID
11:57:04 **Chose Resource - OP20 RESOURCE Time: SDt 2025-05-15, STime 11.82, End Dt 2025-05-15, End Time 11.82 Move Dt 2025-05-16 Move Hr 11.18 . — OpDtlBkProduction
11:57:04 Changing move time for Resource - OP20 RESOURCE from: 0 to 24.00. — OpDtlBkProduction
11:57:04 Reschedule due to Move Time change — operationBackward
11:57:04 Resetting allocationblock!! — operationBackward
11:57:04 Creating new Block calendar for Allocation Block: 1 — operationBackward
11:57:04 Prod Master MakeOperCal
11:57:04 Setup Master MakeOperCal
11:57:04 Backward Scheduling - Job 293772 Asm 0 Opr 20 OpDtl 10 AllocationBlock - 1 For: Enddate - 2025-05-16 EndHour - 11.18 Endtime 1 Setup/Prod/Both B. tmpendtime 627155.18. — OpDtlBkProduction
11:57:04 ***Scheduling resource OP20 RESOURCE for 0 hours — processResourceID
11:57:04 Backward Scheduling OP20 RESOURCE for 0 hours on 2025-05-16 with a EndTime of 11.18 IP-ProcTime 11.18. — processResourceID
11:57:04 Infinitely scheduling OP20 RESOURCE FiniteHorizonDate 2025-04-23 ScheduleDate 2025-05-16 — GetBackwardDateTime
11:57:04 Found 2025-05-16 as a valid working date IP-ProcTime = 40248 — GetBackwardDateTime
11:57:04 Found 2025-05-16 as a valid working date — GetBackwardDateTime
11:57:04 Scheduling resource OP20 RESOURCE starting at time: 2025-05-16 11.18 (getBackwardDateTime) — GetBackwardDateTime
11:57:04 Scheduling resource OP20 RESOURCE for : ScheduleDate 2025-05-16 FirstProdHour 0 LastProdHour 11.18 (getBackwardDateTime) — GetBackwardDateTime
11:57:04 UsingCalendarForMove of 24 Setting Move Due Time. MoveDueDate: 2025-05-16 MoveDueHour: 11.18 — GetBackwardDateTime
11:57:04 Looking for Main production Calendar: OP20 RESOURCE — getWorkingCalendarHours
11:57:04 Looking for Main production Calendar: OP20 RESOURCE — getWorkingCalendarHours
11:57:04 Setting Move start time according to production calendar. MoveStartDate: 2025-05-15 MoveStartHour: 11.82 — GetBackwardDateTime
11:57:04 Looking for previous scheduled time on resource OP20 RESOURCE before 2025-05-15 and a start hour of 11.18 — GetBackwardDateTime
11:57:04 Looking to Schedule 0 Hours Ending on 2025-05-15 and an end hour of 11.82 (getPrevTotalAvailProdTime) — GetPrevTotalAvailProdTime
11:57:04 Zero hours to schedule setting Start date to Start time to 0 (getPrevTotalAvailProdTime) — GetPrevTotalAvailProdTime
11:57:04 Scheduled start time for resource OP20 RESOURCE for 2025-05-15 and a start hour of 11.82 — GetBackwardDateTime
11:57:04 Scheduling Resource OP20 RESOURCE for job 293772 Operation 20 Priority 100 StartDate 2025-05-15 EndDate 2025-05-15. — processResourceID
11:57:04 Setting Queue start time according to production calendar. QueueStartDate: 2025-05-15 QueueStartHour: 11.82 — _addQueueAndMoveTimesToAvailableResource
11:57:04 ***Done Scheduling Resource OP20 RESOURCE for job 293772 Operation 20 Priority 100 StartDate 2025-05-15 EndDate 2025-05-15 Move Date 2025-05-16. — processResourceID
11:57:04 *First available time for Resource OP20 RESOURCE is 2025-05-15 at 42552 (11.82) ending on 2025-05-15 at 11.82 for 0 hours. Move Date 2025-05-16 Move Hour 11.18. — processResourceID
11:57:04 **Chose Resource - OP20 RESOURCE Time: SDt 2025-05-15, STime 11.82, End Dt 2025-05-15, End Time 11.82 Move Dt 2025-05-16 Move Hr 11.18 . — OpDtlBkProduction
11:57:04 ****Created RTU for job 293772 Operation 20 with start date of 2025-05-15 and enddate of 2025-05-15 — createTTResourceTimeUsed
11:57:04 Consolidating calendar with resource OP20 RESOURCE — OpDtlBkProduction
11:57:04 Scheduled Operation 20 - Queue Time: Dt 2025-05-15 Hr 11.82 Start Time: Dt 2025-05-15 Hr 11.82 End Time: Dt2025-05-15 Hr 11.82 Move Time: Dt 2025-05-16 H: 11.18 — doMainProc