Good afternoon,
We still don’t use scheduling in Epicor the way it should be used.
We have setup a resource group simply called ‘labor’. To this we added 30 resources to represent the 30 folks on the floor that can be applied as labor.
Today we are considering what the impacts would be if we changed our labor resources to equate to real people. So instead of Labor1, I would make the resourceID = the clock ID 1234, and description = John Doe. With this approach we think we could apply calendars to individual staff members, and have scheduling take their calendars into account when scheduling jobs/ops.
We realize that this will force us to update all of our jobs and revisions to use the new resources.
What is the consensus on adding actual labor people as resources? Any tips/tricks/ or gotchyas to look out for?
Thanks for your time!
Nate