Is it possible to make the start and due date on the maintenance job entry screen updateable without cussing any errors ?
Start and due dates come from the scheduling system. You should be prompted to schedule the job when you release it. The system will assign start and due dates based on the beginning of the first and end of the last op, respectively. If you’re not using finite scheduling, then the system will backwards schedule from your Req Date. Otherwise, it will fit the job in where it can based on capacity and priority.
Even if you could shove a value in there, it would be overwritten the second the operations are moved around.
Nope… cussing out errors is a part of life.