The best way to backflush is to make sure that the subassemblies are set
up as "Pull as Assembly" and then when you go to close your job, you
check the backflush check box. This will backflush the material in the
subassembly, but not the subassembly itself.
The only problem with this is it might backflush for both operations,
not sure, you might want to test it first.
Michelle de la Vega
Business Applications Manager
Cold Jet, LLC
455 Wards Corner Road
Loveland, Ohio 45140
513-716-6400
513-382-3281 Cell
513-831-1209 (fax)
www.coldjet.com
Setting industry standards in dry ice technology and solutions for over
20 years.
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of mark_wildasin
Sent: Tuesday, April 24, 2007 1:20 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Mass Issuing or BackFlushing Material on 8.00.810C
We have 2 operations - Building and Testing
I know if I relate an operation to a material that it will
automatically backflush when the operation is completed.
Although it does not backflush the materials under our subassemablies
on the job. I do not have operations on the subassemblies because we
just want to log into the job once.
Is there a way to backflush all the materials on the job including the
subassemblies materials at the end of an operation?
Or is there a way to automate mass issue at the end of an operation?
Thank you in advance
Mark
[Non-text portions of this message have been removed]
up as "Pull as Assembly" and then when you go to close your job, you
check the backflush check box. This will backflush the material in the
subassembly, but not the subassembly itself.
The only problem with this is it might backflush for both operations,
not sure, you might want to test it first.
Michelle de la Vega
Business Applications Manager
Cold Jet, LLC
455 Wards Corner Road
Loveland, Ohio 45140
513-716-6400
513-382-3281 Cell
513-831-1209 (fax)
www.coldjet.com
Setting industry standards in dry ice technology and solutions for over
20 years.
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of mark_wildasin
Sent: Tuesday, April 24, 2007 1:20 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Mass Issuing or BackFlushing Material on 8.00.810C
We have 2 operations - Building and Testing
I know if I relate an operation to a material that it will
automatically backflush when the operation is completed.
Although it does not backflush the materials under our subassemablies
on the job. I do not have operations on the subassemblies because we
just want to log into the job once.
Is there a way to backflush all the materials on the job including the
subassemblies materials at the end of an operation?
Or is there a way to automate mass issue at the end of an operation?
Thank you in advance
Mark
[Non-text portions of this message have been removed]