I am trying to add misc. charges to a Field Service Job for travel and mileage. Does anyone know where and how to do this?
It lives as a job material on the service job. The information then needs to be filled in on the Material Service tab of the job material
I am on the Material Service Tab on Job Material. I entered the part price. I need to add for travel hours and mileage. How do I get these additional charges added?
Do I need to add additional material for each additional misc. charge?
Add two materials (one for travel and one for mileage). Under each material, fill in the information on the Material service tab.
unfortunately yes
I got it to work. Thank you very much for the help! It has been at least 6 years since I worked in Field Service. I am knocking the rust off! 