Move Process Set to New Environment

Does anyone have a suggestion on how to migrate a process set from one environment to another? I’ve built out one with 800 schedule function calls in a test environment I would like to be able to roll into the next test environment and Prod without having to manually recreate them. I would like to not have to manually recreate it, but I have not found any way to DMT it or paste-insert.

Have you tried an updatable BAQ?
Create a temp dashboard that you load them into Live?

I tried that, but it didn’t seem to take with a simple database update. I think I’d have to figure out how to use the BO to update the same way the UI does. I’ll try that later after I get through a priority assignment, but I wanted to thank you for the suggestion and let you know I’m trying it. Will update if I find success with it.