MRP against Non-nettable bin

MRP ignores non-nettable inventory.

--- On Wed, 10/29/08, Tony Hughes <thughes281@...> wrote:

From: Tony Hughes <thughes281@...>
Subject: [Vantage] MRP against Non-nettable bin
To: vantage@yahoogroups.com
Date: Wednesday, October 29, 2008, 1:43 PM






Does MRP consider inventory in a non-nettable bin?
If minimum for a part is 10, I have 5 in a nettable, 5 in a non-nettable, will MRP suggest 5 or not?
I can test this after MRP runs overnight, but if anyone knows.

Thank you,

Tony

[Non-text portions of this message have been removed]
Does MRP consider inventory in a non-nettable bin?
If minimum for a part is 10, I have 5 in a nettable, 5 in a non-nettable, will MRP suggest 5 or not?
I can test this after MRP runs overnight, but if anyone knows.

Thank you,

Tony





[Non-text portions of this message have been removed]
Anything non-nettable is not in the on-hand qty and MRP would ignore it.
MRP does not look at bins. Neither does MRP look at on-hand for anything
that is non-stock when looking at creating jobs or evaluating materials.



Charlie Smith

Smith Business Services / 2W Technologies LLC

www.vistaconsultant.com <http://www.vistaconsultant.com/> /
www.2WTech.com









From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Tony Hughes
Sent: Wednesday, October 29, 2008 1:43 PM
To: vantage@yahoogroups.com
Subject: [Vantage] MRP against Non-nettable bin



Does MRP consider inventory in a non-nettable bin?
If minimum for a part is 10, I have 5 in a nettable, 5 in a
non-nettable, will MRP suggest 5 or not?
I can test this after MRP runs overnight, but if anyone knows.

Thank you,

Tony

[Non-text portions of this message have been removed]