Thanks Bill. Looks like you are running things very similar to us.
Now that we are running things as a three step, MRP, Global Scheduling Order, then Global Scheduling, we haven't had a lockup. We also found running only 1 process for each step works better too. Takes a bit longer, but we are still less than an hour to complete everything using regen.
Now that we are running things as a three step, MRP, Global Scheduling Order, then Global Scheduling, we haven't had a lockup. We also found running only 1 process for each step works better too. Takes a bit longer, but we are still less than an hour to complete everything using regen.
--- In vantage@yahoogroups.com, "Bill" <wmitchell@...> wrote:
>
> 1. How long does MRP take to run, using a) Regenerative b) Net Change?
> Never use net change, always regen. Its run Mon to Thurs early morning. It takes about 30 mins to run. We have about 6000 parts on the system and BOMs are generally no more than 5 or 6 levels.
>
> 3. Yes we use finite scheduling
>
> 4. 1 process for MRP and 1 scheduler
>
> 5. We do occasionally get lock ups. As part of the daily tasks we check the appserver for stuck processes, deleting those usually clears things.
>
> 7. We log MRP and schedule activity
>
> 8. Parts are constrained.
>
> Any other issues ? Is anyone aware of a third party scheduling tool which interfaces with Vantage (we run 8.03.408) ?
> Our experience with MRP is mixed to say the least. Initially it produced vast volumes of spurious suggestions which with the help of an outside consultant we eventually managed to resolve, however it still leaves us scratching our heads at times.
> Do people in this forum use the scheduling boards ? Or do you have something else that can be used to manipulate data in a similar sort of graphical way ?
>
> Thanks
>
> Bill
>
>
>
>
>
> --- In vantage@yahoogroups.com, "Tim Vonderhaar" <tvonderhaar@> wrote:
> >
> > We are running some pilot MRP tests and are struggling a bit to understand if things are working as expected. We are reading through the MRP Tech Ref Guide, but would like to know what others have actually experienced in their organization. I understand that this isn't a one size fits all thing, but would like to get a few points of reference.
> >
> > 1) How long does MRP take to run, using a) Regenerative b) Net Change?
> > 2) How often do you run Regenerative?
> > 3) Do you use Finite Scheduling?
> > 4) What number of MRP processes do you use?
> > 5) What number of schedulers do you use?
> > 6) Have you ever had the MRP process lock up? If so, how can one tell?
> > 7) Do you use logging? If so, what setting do you use? a) basic b) MRP c) MRP and Scheduling?
> > 8) Are your parts constrained?
> > 9) Do you use APS?
> > 10) Any lessons learned?
> >
> > Thanks,
> > Tim
> >
>